Pechanga Pulls in GEC2 for Media Boards at SoFi Stadium

Posted by GEC2 on Dec 28, 2021 3:15:00 PM

GEC2 partnered with Shawmut to complete the installations for wiring and outlets on the 52 digital media boards at SoFi Stadium. 

This project was awarded to GEC2 in late October '21 and was completed ahead of schedule, in just under 7 weeks! Scopes for the team of 4, lead by Arlyn Rambayon and Gerry Aaron, consisted of adding a 480v-208/120volt 75KAV. XFORM to feed a new 225amp Branch Circuit Board 450ft away. The team also installed (2) 3” parallel with ground feed for the voltage drop and fiber cabling.

Topics: SoFi, Installation, Los Angeles Rams, Los Angeles Chargers, Stadium, Partner, Media Boards